The repair involved the installation of 50 no. 2t – 4t rock bags, 101 no. 5t grout bags, 170m3 of in-situ tremie underwater concrete stitch pours and 1,400t of 3t rock armour. Works were carried out from a spud leg barge and to maintain continuity of the Stena Line ferry service to Cairnryan, works were planned and carried out between sailings in 60-minute working windows.