The £4.3 million project to install a new ro-ro ferry terminal had to be completed during a planned shut down over the festive period. There were seven berths including a roll-on roll-off berth which required upgrading for use by larger vessels. Charles Brand was commissioned to design and construct a new floating pontoon and two new linkspan bridges, two berthing dolphins (including walkways, fendering and mooring points) and reclamation works.
The works had to be co-ordinated with port activity including the berthing and mooring requirements of vessels and tugs and onshore traffic movements, with tidal conditions dictating the time slots available. Specific health and safety methods and working systems were developed to prevent falls into the water or onto vessels below.
The project was delivered successfully without incident or accident thanks to our rigorous safety training and procedures.
As Civil Engineering Director, Paddy leads the delivery of projects across a wide range of sectors including Roads, Railways, Flood Alleviation, Marine, Utilities and Water. A graduate of the Queens University of Belfast, Paddy is a Chartered Civil Engineer, specialising in civil engineering infrastructure.