Fibrus Project Stratum Northern Ireland

Fibrus Project Stratum Northern Ireland

Project Stratum was developed to improve broadband connectivity to 85,000 premises across NI, primarily in rural areas and was predominantly Government funded.

Charles Brand were responsible for delivering full fibre broadband to 57,300 premises across NI, with up to 110 crews deployed at any given time. Close and regular liaison with Key stakeholders including DFI roads, local Councils, utility providers and landowners was vital to the success of the Project. 

Client

Fibrus

Value

£56.1M

Duration

37 months

The works involved:

  • 302km of new duct installed
  • 11,000 duct blockage repairs completed
  • 22,000 new poles installed
  • 940km of tree trimming cut
  • 3397km of OH cabling
  • 1605km of UG cabling installed
Key Contact
View Full Team
Anthony Martin

Anthony Martin

Telecoms Director
Read bio

Anthony Martin

Telecoms Director

As Director of Telecommunications, Anthony (Tony) specialises in ‘Fibre To The Home’. His collaborative approach allows him to lead multi-disciplinary teams throughout the UK and Ireland.